Cartosat-2E + 30 микроспутников – PSLV-C38 – Шрихарикота – 23.06.2017 03:59 UTC

Автор che wi, 14.04.2017 09:17:07

« назад - далее »

0 Пользователи и 1 гость просматривают эту тему.

tnt22

Трансляция пуска - Doordarshan National
ЦитироватьThe Launch of PSLV - C38 / CARTOSAT-2 Series Satellite- Live

DoordarshanNational

Запланировано на 23 июн. 2017 г.


tnt22

http://isro.gov.in/update/22-jun-2017/mobile-service-tower-mst-withdrawal-to-parking-end-completed-preparations
ЦитироватьJun 22, 2017
Mobile Service Tower (MST) withdrawal to parking end is completed. Preparations for propellant filling operation of Second Stage (PS2) are in progress

tnt22


tnt22

http://www.thehindu.com/sci-tech/isro-plans-complex-manoeuvres/article19127342.ece
ЦитироватьISRO plans complex manoeuvres
T. Nandakumar
Thiruvananthapuram, June 22, 2017 21:34 IST
 Updated: June 22, 2017 21:36 IST
Engines in the fourth stage will be reignited three times

The countdown for the PSLV-C38 mission began on Thursday morning, engineers at ISRO were preparing to execute a series of complex manoeuvres for the shutdown and reignition of the rocket engines in space.

The engines in the fourth stage will be reignited three times, in a bid to master the technique that will enable ISRO to inject satellites into different orbits in a single launch. "It will be a validation of the technique that was tested in the PSLV-C34 mission and deployed in the subsequent C35 mission", says B. Jayakumar, PSLV project director. The exercise will be conducted after all 31 satellites on PSLV-C38 have been injected into orbit.

"Once the last satellite has been separated from the rocket at a height of 520 km, the fourth stage of the rocket (PS4) comprising two liquid propellant engines will be shut down and reignited three times," Mr. Jayakumar told The Hindu. While the first two firings are expected to last about six seconds each, the third restart is likely to fire up to 40 seconds.

The multiple reignition of the on board engines will validate the technique and provide ISRO with the mission flexibility to inject satellites into three different orbits in a single flight to reduce the launch cost and save time.

...

tnt22


tnt22

Цитировать06/23/2017 04:53
ISRO reports the Polar Satellite Launch Vehicle is fully fueled for today's launch. The final step was loading of more than 92,000 pounds (42 metric tons) of hydrazine and nitrogen tetroxide into the PSLV's second stage.

Technicians filled the PSLV's fourth stage with its storable liquid propellant earlier in the 28-hour countdown sequence. The first and third stages of the rocket are fueled by pre-packed solid propellants.


tnt22

Цитировать06/23/2017 05:59
T-minus 60 minutes. There are no problems reported in the countdown, and launch remains on track for 0359 GMT (11:59 p.m. EDT).
Some statistics on today's flight
    [/li]
  • 40th PSLV mission
  • 17th launch in PSLV XL configuration
  • 4th Indian launch of 2017
  • 2nd PSLV flight of 2017


tnt22





tnt22


tnt22

Цитировать06/23/2017 06:42
Weather conditions are ideal for a launch at the Satish Dhawan Space Center, a spaceport on Sriharikota Island on India'a east coast approximately 50 miles north of Chennai.

tnt22

Цитировать Spaceflight101 LIVE‏ @S101_Live 37 сек. назад

L-16 Minutes: Final Status Checks are in progress before authorization for the automated countdown is given. #PSLV

tnt22

Цитировать06/23/2017 06:44
The launch authorization board has given the green light for the final terminal countdown sequence.

tnt22

Цитировать06/23/2017 06:46
The vehicle director has authorized the start of the final automated launch sequence.

tnt22

Цитировать Spaceflight101 LIVE‏ @S101_Live 1 мин. назад

L-13 Minutes: One Minute to the start of the Terminal Countdown Sequence to prepare #PSLV for liftoff.

tnt22